A change request is a formal proposal to modify any document, deliverable or baseline.
Several project management processes may involve a change request.
Perform integrated change control is the process of reviewing all change requests and approving the changes. This process happens throughout the project for integrating change requests.
The approved change request may be a
The approved changes are implemented through the direct and manage project work process, to achieve the project’s objectives.
Table of Contents
Project management plan should be baselined so that the actual project performance can be measured against the baseline. Before baselining the project management plan, it can be changed as many times as you want without going through any change control process. But, once the baseline is agreed, any further changes can happen only through formal change control process.
While developing the project management plan, we also should establish which project documents will be subject to the formal change control process.
Change management plan, a component of the project management plan, describes how the change requests will be formally authorized and incorporated.
Change log is a project document. The change log contains the status of all change requests.
In an Agile/ adaptive environment, the project manager’s focus is on ensuring the team has the ability to respond to changes.
The first thing to do as a Project Manager is to minimize change requests in a project. You have to work to influence the causes of change requests.
You need to understand that, in spite of your efforts, changes are inevitable in a project.
If you get a change request, the following are the suggested steps to address the change request:
You should also note that depending on the level of authority given to the project manager, the change requests may be reviewed and approved by the project manager himself/ herself.
Do you know how many processes take change requests as an input?
It is only ONE process that takes change request as an input. Any guess which process it is?
Did you say Perform Integrated Change Control process? Yes, you are right.
Perform Integrated Change Control process is the only process where you will see change requests as an input. This makes sense as this is the only process where the change requests are reviewed and approved/ deferred/ rejected.
So, remember, if you see change requests as an input in any of the PMP exam question, the process should be Perform Integrated Change Control.
Change requests can be generated throughout the project. PMBOK Guide has listed 25 processes where change requests may be generated. They are:
You do not need to remember all the 24 processes.
But, you should remember that all Monitoring and Controlling processes (except 4.6 Perform Integrated Change Control) will generate Change requests.
Don’t get confused between Change requests and Approved change requests. Approved change requests are inputs to three processes namely
How many processes do you think can approve change requests? Only ONE.
Which process is that? Yes, it is Perform Integrated Change Control.
As we have discussed throughout this article, the change requests are reviewed and approved in the Perform Integrated Change Control process. So, naturally, the output of this process should be Approved change requests.
Changes are an integral part of any project. It is the responsibility of the project manager to adequately manage the changes in a project.
Do you follow the above steps in your project?
Do you think the above flow chart helps you in your PMP exam preparation?
Leave your thoughts.
This article was triggered by an e-mail from Sarita, extract of which is shown below:
Your posts are very helpful.
Can you pls share the complete step by step process to follow in case of change management. As this is a very imp topic and many qs come in the exam.
If you have any similar requirements, you can drop me a mail at pmdrill.com@gmail.com. I will try my best to address them in my upcoming articles.
I got this lessons learned feedback from a candidate, who wants to remain anonymous. So,…
Project management primarily involves planning, executing and monitoring/ controlling activities. While a project could be…
While you might find extensive content online for the Project Management Professional (PMP) examination, it…
If you do an online search for PMP training programme, you'll find hundreds of options…
On 19 Mar 2019, I received a phone call from Venkataraghavan. Venkat attended my PMP…
Haitham Al-Kahlani feels the PMP examination is "Scary". I met Haitham at PM Master Prep's…
View Comments
Dear sir
Change request is not a output 4.6 (but input 4,6 => output approved CR).
So i think M&C has out CR, except 4.6
Absolutely Pham Tu. Thanks for highlighting that error. I have corrected it now.
Sir, this article was very informative and useful. Kindly write a blog on 27 data analysis techniques as well if possible. Thanks for this blog !!!
Thanks Akhilesh. Will add "27 data analysis techniques" to my to-do list.